|
The Fundamental
Flaw in the "pre-Northridge" Moment Frame Connection
by
Professor Emeritus Ralph M. Richard, Ph.D., P.E.
University of Arizona, Tucson, AZ |
The popular field welded–field bolted beam-to-column moment frame
connection, shown in both of the current AISC LRFD and ASD steel
design manuals, has become known as the “pre-Northridge” connection.
As a result of surveys of damaged buildings made subsequent to the
1994 Northridge, CA earthquake, it was concluded by the Structural
Engineers Association of California (1996 SEAOC Blue Book
Commentary) that the pre-Northridge connection is fundamentally
flawed and should not be used in the construction of new seismic
moment frames. This conclusion was based upon (1) this connection's
modes of fracture, (2) an historic review of the 1960 - 1990 tests
made at the University of California and Lehigh University that led
to this connection's design rationale, and (3) ATC-24 protocol tests
in the SAC/FEMA research program.
Extensive finite element analyses and strain gage data from ATC-24
tests by Seismic Structural Design Associates, Inc. (SSDA) of this
pre-Northridge connection made subsequent to the Northridge
earthquake in 1994 and 1995 showed large stress and strain gradients
horizontally across and vertically through the beam flanges and
welds at the face of the column. These large flange stress and
strain gradients are caused by a very large component of the seismic
shear, typically 50% or more, that is carried by the beam flanges.
It is these flange shear forces that produce a prying moment in the
welds and flanges at the face of the column and at the weld access
holes that led to the weld and flange fractures and to the column
flange divot modes of connection fracture. Moreover, the large
plastic strains associated with these prying moments significantly
reduce the fatigue life of the connection (Richard, R.M., et al.,
"Accumulated Seismic Connection Damage Based upon Full Scale Low
Cycle Fatigue Connection Tests", Proceedings of the Structural
Engineers Association of California 70th Annual Convention, p.
43-48, September 27-29, 2001). Additionally, failure analyses of the
SAC ATC-24 test specimens at the University of Michigan and at
Lehigh University demonstrated that fatigue cracks initiated and
propagated in all the tested specimens (John M. Barsom, "SAC Steel
Project 7.1.3", May, 2000).
A six year $12,000,000 seismic research program by SAC (a consortium
of three organizations, (1) SEAOC, (2) the Applied Technology
Council, and (3) the Consortium of Universities for Research in
Earthquake Engineering), which was funded by the Federal Emergency
Management Agency (FEMA), the American Institute of Steel
Construction (AISC), and the National Science Foundation (NSF), was
concluded in August 2000. A series of seismic connection design
seminars were then given that were funded by FEMA. Attendees at
these seminars were provided with a set of notes entitled "New
Recommended Seismic Design Criteria for Steel Moment Frame
Buildings: Speakers Slide's". In these notes it is stated that the
large component of seismic shear, typically 50%, and its prying
effects still exist in the beam flanges and welds of the SAC
pre-qualified Reduced Beam Section (RBS), the WUF-W, and the WUF-B
connections, which use the "standard" unreinforced flange connection
(James Malley, p. 5-19; Stephen Mahin, p. 3-14,15). However, the
published FEMA-350, July 2000, design rationale for the RBS, WUF-W,
and WUF-B connections does not account for these large flange shears
wherein all of the shear is assumed to be resisted by the beam web
connection. Specifically, the beam web connection design rationale
in FEMA-350 for the RBS is given on p. 3-41, design steps 4 and 5;
for the WUF-W on p. 3-31; and for the WUF-B on p. 3-28, design steps
5 and 6.
Historically, the departure of the connection force distribution
from elementary beam theory, wherein the "flanges carry the moment
and the web carries the shear", was first analytically determined by
Professor Y.Y. Yu in 1959 (Jr. of Applied Mechanics, Vol. 26, No. 3,
pp. 415-429, 1959). Moreover, in 1968 John F. Abel and Egor P. Popov
of the University of California, using the finite element method,
confirmed Yu's analytical solution that showed 100% of the beam
shear is carried by the flanges in a cantilever beam at a rigid
support (AFFDL T.R. No. 68-150, pp. 213-245, 1968). Additionally, in
1970 Popov and Stevens reported that in their connection test of a
W18x50 beam "…with welded flanges only and no web attachment
whatsoever, exceeded in capacity the yield moment while transmitting
a large shear." They further stated that "Since the welded flanges
appear to transfer to the column most of the beam shear, the precise
number of bolts required for hybrid connections needs further
investigation" (University of California, Berkeley, EERC Report No.
70-3, July 1970).
An alternative connection design using vertical beam flange fins to
account for the flange shear has been tested successfully by SAC (AISC
Engineering Jr., p. 43, 2nd Qtr., 1997 and AISC Engineering Jr., p.
31, 1st Qtr., 2000) and by Zekioglu, A. et al., "Designing After
Northridge", Modern Steel Construction, March 1997, p. 36-42). SAC
apparently has not recommended the use of vertical flange fins
because of their increased cost of fabrication.
|